On Target Morrisville-Carpenter Road Improvements Project
40% Complete
CY Q2-21
Last Updated: 07/19/2021
Milestones:
Complete a) Engineering/Design funding approved
Complete b) Right-of-way acquisition funding approved
Complete c) LAPP Funding received for right-of-way acquisition and construction funding
Complete d) Right-of-way acquisitions
Complete e) Right-of-way acquisitions
On Target f) Start of Construction
Future Data g) Road construction complete

Legend: Complete | On Target | Near Target | Below Target | Future Data | No Data

Legend: Complete
On Target
Near Target
Below Target
Future Data
No Data

The widening of Morrisville Carpenter Road, a state-owned road, will make a significant impact in the flow of traffic in the Town of Morrisville and surrounding region. This road widening project has been needed for many years, but the Morrisville-Carpenter road widening project did not compete well with other area projects when scored for state funding prioritization and funding was not awarded. In 2015, the Town Council made a strategic decision to  invest in the road design to help the project score higher. This effort was successful. Funding for construction of the road widening was awarded in October 2017. The Town received authorization from NCDOT in August 2020 to re-restart the construction bidding process.  The project was advertised in September. After Town Council approval and NCDOT concurrence, the Town will sign a contract with the lowest responsible bidder. Construction is expected to start in January of 2021. The construction duration is 18 months, and construction is anticipated to be completed in Summer 2022.

Access to homes and businesses along Morrisville-Carpenter Road during construction will remain open, but may be limited during certain phases of construction.  The Town has worked with NCDOT and its engineer to phase the construction so that the road will remain open to two-way travel, but there will be periods when lane closures will have to occur that may limit access.  Any lane closures that do occur will only occur between 9am and 4pm, with two travel lanes (one in each direction) open during the morning and afternoon peak hours. 

There will be a weekend road closure (from 8pm on Friday to 6am on Monday), between the railroad tracks and Town Hall Drive, near the completion of the project in order to allow the contractors to safely install a new median in the area.  While the timing of this closure is unknown at this point, the Town will post notice of the road closure in advance using the Town’s website, email lists, social media and electronic message boards.  During this closure, a detour will be posted advising traffic of alternate access.


Phase 1 work is in progress.  Most of the Phase 1 work is near the Morrisville Carpenter Rd./Town Hall Dr. intersection, between Town Hall drive and Misty Groves Circle, and along Franklin Upchurch, Sr. St. Variable message boards have been installed and Communications staff share weekly updates to neighboring HOAs and those signed up to receive updates.