Major Projects
Unique construction projects that provide improvements/additions such as buildings, facilities and infrastructure. Projects listed are in progress, nearing completion, or in advanced development stage.
Milestones:
a) NC54 road widening
b) Railroad Crossing work at NC54/McCrimmon Parkway
c) Associated intersection improvements on Airport Blvd, Aviation Pkwy and Evans Rd
d) Construction of new four-lane, median-divided roadway, from Airport Blvd to Aviation Pkwy at Evans Rd
Legend: Complete |
On Target |
Near Target |
Below Target |
Future Data |
No Data
Legend: Complete
On Target
Near Target
Below Target
Future Data
No Data
Following voter approval of the Transportation Bond Referendum in November 2012, the Town of Morrisville began work on the McCrimmon Parkway Extension. The Town partnered with NCDOT on the project in order to leverage state transportation funding with the Town's bond funding, resulting in a two-phase project. Phase One construction was administered by the Town, with Phase Two construction administered by NCDOT.
Town of Morrisville Phase
- Extend McCrimmon Parkway east from NC 54 to the existing section of McCrimmon Parkway at Perimeter Park Drive as a four lane roadway with sidewalks/multi-use paths on each side and bicycle accommodations
- Widen McCrimmon Parkway across the railroad tracks near NC 54 to add a left-turn lane and right-turn lane onto NC 54, re-striping the existing eastbound lane to a through lane
- Associated intersection improvements on NC 54 and Perimeter Park Drive
NCDOT Phase
- Construct a new four-lane, median-divided roadway with 8' multi-use paths and 5' bicycle lanes from Airport Boulevard to Aviation Parkway at Evans Road
- Install a Traffic Signal at the Airport Boulevard/McCrimmon Parkway intersection
- Associated intersection improvements on Airport Boulevard, Aviation Parkway and Evans Road
Town of Morrisville, NC | 100 Town Hall Drive, Morrisville, NC 27560 | 919-463-6200